[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119007":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119007,789,1,"单选题","工序施工条件控制是指对工序施工活动的()质量进行有效控制。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","合同条件和法规条件",false,{"key":16,"text":17,"correct":14},"B","工艺顺序和组织条件",{"key":19,"text":20,"correct":21},"C","投入要素和环境条件",true,{"key":23,"text":24,"correct":14},"D","工期条件与赶工措施","2021\u002F2020教材P167页 工序施工条件就是控制工序活动的各种投入要素质量和环境条件质量。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]