[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119004":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119004,789,1,"单选题","测量控制方案应在项目开工前编制，经( )批准后实施。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目经理",false,{"key":16,"text":17,"correct":14},"B","监理工程师",{"key":19,"text":20,"correct":14},"C","建设单位项目负责人",{"key":22,"text":23,"correct":24},"D","项目技术负责人",true,"2021\u002F2020教材P166页 项目开工前应编制测量控制方案，经项目技术负责人批准后实施。对相关部门提供的测量控制点应在施工准备阶段做好复核工作，经审批后进行施工测量放线， 并保存测量记录。在施工过程中应对设置的测量控制点、线妥善保护，不准擅自移动。施工过程中必须认真进行施工测量复核工作，这是施工单位应履行的技术工作职责， 其复核结果应报送监理工程师复验确认后，方能进行后续相关工序的施工。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]