[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119002":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1119002,789,1,"单选题","每一分部工程开工前应进行作业技术交底，技术交底应由施工项目技术人员编制，并经（）批准实施。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目技术负责人",true,{"key":16,"text":17,"correct":18},"B","项目经理",false,{"key":20,"text":21,"correct":18},"C","施工企业技术负责人",{"key":23,"text":24,"correct":18},"D","业主代表","2021\u002F2020教材P166页 每一分部工程开工前均应进行作业技术交底。技术交底书应由施工项目技术人员编制，并经项目技术负责人批准实施。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]