[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119000":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119000,789,1,"单选题","技术交底的内容主要包括( )，施工中应注意的问题，可能出现意外的措施及应急方案，文明施工和安全防护措施以及成品保护要求。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","任务分配、施工方法、质量标准和验收标准",false,{"key":16,"text":17,"correct":18},"B","任务范围、施工方法、质量标准和验收标准",true,{"key":20,"text":21,"correct":14},"C","任务分配、施工方法、施工要求和验收标准",{"key":23,"text":24,"correct":14},"D","任务范围、施工方法、施工要求和验收标准","2021\u002F2020教材P166页 一、技术交底 技术交底的内容主要包括：任务范围、施工方法、质量标准和验收标准，施工中应注意的问题，可能出现意外的措施及应急方案，文明施工和安全防护措施以及成品保护要求等。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]