[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118993":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118993,789,1,"单选题","施工承包企业应对建设单位提供的原始坐标点、基准线和水准点等测量控制点进行复核，并将复测结果上报()审批，批准后才能建立施工测量控制网，进行工程定位和标高基准的控制。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目技术负责人",false,{"key":16,"text":17,"correct":14},"B","企业技术负责人",{"key":19,"text":20,"correct":14},"C","业主",{"key":22,"text":23,"correct":24},"D","监理工程师",true,"2021\u002F2020教材P164页 施工单位必须对建设单位提供的原始坐标点 、基准线和水准点等测量控制 点线进行复核 ，并将复测结果上报监理工程师审核 ，批准后施工单位才能据此建立施工测量控制网 ，进行工程定位和标高基准的控制。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]