[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118971":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118971,789,1,"单选题","施工单位必须对建设单位提供的原始基准点、基准线和标高等测量控制点复核，并将复测结果上报()审核。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目经理",false,{"key":16,"text":17,"correct":14},"B","业主",{"key":19,"text":20,"correct":21},"C","监理工程师",true,{"key":23,"text":24,"correct":14},"D","建设单位技术负责人","2021\u002F2020教材P164页 工程测量放线是建设工程产品由设计转化为实物的第一步。施工测量质量的好坏，直 接决定工程的定位和标高是否正确，并且制约施工过程有关工序的质量。因此，施工单位 必须对建设单位提供的原始坐标点、基准线和水准点等测量控制点线进行复核，并将复测结果上报监理工程师审核，批准后施工单位才能据此建立施工测量控制网，进行工程定位 和标高基准的控制。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]