[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118964":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118964,789,1,"单选题","某施工单位承建某建设工程项目，该项目建设工期很紧，为了保证工程建设的顺利进行，建设单位向施工单位及时提供了原始基准点、基准线和标高等测量控制点等资料，施工单位应()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","按照建设单位提供的资料及时开始施工",false,{"key":16,"text":17,"correct":18},"B","首先进行复核，然后将复测结果报监理单位审核",true,{"key":20,"text":21,"correct":14},"C","首先进行复核，然后将复测结果报设计单位审核",{"key":23,"text":24,"correct":14},"D","首先进行复核，然后将复测结果报勘察单位审核","2021\u002F2020教材P164页 按照工程定位和标高基准控制的要求，施工单位必须对建设单位提供的原始基准点、基准线和标高等测量控制点进行复核，并将复测结果上报监理工程师审核。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]