[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118944":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118944,789,1,"单选题","在施工现场质量检查的实测法中，通过“吊”进行质量检验的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","检查垂直度",true,{"key":16,"text":17,"correct":18},"B","墙面的平整度",false,{"key":20,"text":21,"correct":18},"C","踢脚线的垂直度",{"key":23,"text":24,"correct":18},"D","确定轴线位置是否偏离","2021\u002F2020教材P163页 ②实测法：吊，就是用托线板以及线锤吊线检查垂直度。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]