[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118890":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118890,789,1,"单选题","工程项目质量计划可以按()分为质量工作计划和质量成本计划。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","内容",true,{"key":16,"text":17,"correct":18},"B","用途",false,{"key":20,"text":21,"correct":18},"C","质量目标",{"key":23,"text":24,"correct":18},"D","工期","2021\u002F2020教材P157页 工程项目施工质量计划可以按内容分为施工质量工作计划和施工质量成本计划。其他选项错误。考点来源:2Z104020第四章施工质量控制第二节施工质量管理体系的建立和运行",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]