[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118884":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118884,789,1,"单选题","建设工程项目质量管理的PDCA循环工作原理中，与计划比较执行过程中是否产生的偏差属于（）环节的工作。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","计划",false,{"key":16,"text":17,"correct":14},"B","实施",{"key":19,"text":20,"correct":21},"C","检查",true,{"key":23,"text":24,"correct":14},"D","处理","2021\u002F2020教材P159页 检查是对照计划，检查执行的情况和效果，及时发现计划执行过程中的偏差和问题。检查一般包括两个方面：一是检查是否严格执行了计划的行动方案，检查实际条件是否发生了变化，总结成功执行的经验，查明没按计划执行的原因；二是检査计划执行的结果，即施工质量是否达到标准的要求，并对此进行评价和确认。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]