[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118878":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118878,789,1,"单选题","施工质量保证体系的运行，按照PDCA循环原理展开，其中”C”是指()",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","确定质量方针、目标",false,{"key":16,"text":17,"correct":14},"B","计划行动方案交底和按规定要求展开施工作业活动",{"key":19,"text":20,"correct":21},"C","检查是否执行了计划的行动方案",true,{"key":23,"text":24,"correct":14},"D","采取纠偏措施","2021\u002F2020教材P158页 施工质量保证体系的运行 1.计划（Plan) 2.实施（Do) 3.检查（Check)检查就是对照计划，检查执行的情况和效果，及时发现计划执行过程中的偏差和问题 4.处理（Action)。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]