[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118875":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118875,789,1,"单选题","建设工程项目质量管理的PDCA循环中，质量计划阶段的主要任务是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","明确质量目标并制定实现目标的措施与行动方案",true,{"key":16,"text":17,"correct":18},"B","展开工程项目的施工作业技术活动",false,{"key":20,"text":21,"correct":18},"C","对计划实施过程进行科学管理",{"key":23,"text":24,"correct":18},"D","对质量问题进行原因分析，采取措施予以纠正","2021\u002F2020教材P158页 1。计划（Plan) 计划是质量管理的首要环节，通过计划，确定质量管理的方针、目标，以及实现方针、目标的措施和行动方案。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]