[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118869":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118869,789,1,"单选题","施工质量保证体系运行的重心是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","质量计划",false,{"key":16,"text":17,"correct":18},"B","过程管理",true,{"key":20,"text":21,"correct":14},"C","PDCA循环",{"key":23,"text":24,"correct":14},"D","质量管理八项原则","2021\u002F2020教材P158页 施工质量保证体系的运行，应以质量计划为主线，以过程管理为重心，按照PDCA循环的原理，按照计划、实施、检查和处理的步骤展开控制。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]