[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118852":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118852,789,1,"单选题","施工质量的过程控制要求高主要是因为建筑产品生产过程()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","影响因素多",false,{"key":16,"text":17,"correct":14},"B","不可预见的因素多",{"key":19,"text":20,"correct":21},"C","工序交接多、隐蔽工程多",true,{"key":23,"text":24,"correct":14},"D","质量满足的要求既有明示的、又有隐含的","2021\u002F2020教材P155页 工程项目在施工过程中，由于工序衔接多、中间交接多、隐蔽工程多，施工质量具有一定的过程性和隐蔽性。在施工质量控制工作中，必须加强对施工过程的质量检查，及时发现和整改存在的质量问题，避免事后从表面进行检查。过程结束后的检查，难以发现在过程中产生、又被隐蔽了的质量隐患。故选择C选项。选项A、B、D不是质量的过程控制要求高的主要原因。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]