[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118843":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118843,789,1,"单选题","工程项目在施工过程中，由于工序衔接多、中间交接多、隐蔽工程多，施工质量具有一定的过程性和隐蔽性，因此施工质量控制具有()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","控制因素多",false,{"key":16,"text":17,"correct":18},"B","过程控制要求高",true,{"key":20,"text":21,"correct":14},"C","终检局限大",{"key":23,"text":24,"correct":14},"D","控制难度大","2021\u002F2020教材P155页 （3）过程要求控制高：工程项目的施工过程，工序衔接多、中间交接多、隐蔽工程多，施工质量具有一定的过程性和隐蔽性。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]