[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118835":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118835,789,1,"单选题","某工程在施工过程中，地下水位比较高，若在雨期进行基坑开挖，遇到连续降雨或排水困难，就会引起基坑塌方或地基受水浸泡影响承载力，这属于（）对工程质量的影响。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","方法的因素",false,{"key":16,"text":17,"correct":14},"B","施工作业环境因素",{"key":19,"text":20,"correct":21},"C","现场自然环境因素",true,{"key":23,"text":24,"correct":14},"D","施工质量管理环境因素","2021\u002F2020教材P154页 施工现场自然 环境因素：主要指工程地质、水文、气 象条件和周边建筑、地下障碍物以及其他不可抗力等对施工质量的影响因素。例如，在地下水位高的地区，若在雨季进行基坑开挖，遇到连续降雨或排水困难，就会引起基坑塌方或地基受水浸泡影响承载力等；在寒冷地区冬期施工措 施不当，工程会因受到冻融而影响质量；在基层未干燥或大风天进行卷材屋面防水层的施工，就会导致粘贴不牢及空鼓等质量问题。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]