[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118807":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118807,789,1,"单选题","如下所示双代号网络计划（不考虑要求工期），工作E的最迟开始时间是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","4",false,{"key":16,"text":17,"correct":14},"B","11",{"key":19,"text":20,"correct":14},"C","6",{"key":22,"text":23,"correct":24},"D","7",true,"2021\u002F2020教材P141页 关键线路1-2-3-5-6为14天F工作的最迟完成时间为14天，最迟开始时间为14-4=10天F工作的最迟开始时间为E工作最迟完成时间所以为10天E工作最迟开始时间为10-3=7天",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]