[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118806":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118806,789,1,"单选题","在网络计划中，若某项工作的（）最小，则该工作必为关键工作。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","持续时间",false,{"key":16,"text":17,"correct":14},"B","自由时差",{"key":19,"text":20,"correct":21},"C","总时差",true,{"key":23,"text":24,"correct":14},"D","时间间隔","2021\u002F2020教材P141页 网络计划中总时差最小的工作是关键工作。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]