[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118805":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118805,789,1,"单选题","某建设工程施工进度计划如下图所示（时间单位：天），则该进度计划的计算工期是()天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","20",false,{"key":16,"text":17,"correct":14},"B","23",{"key":19,"text":20,"correct":21},"C","21",true,{"key":23,"text":24,"correct":14},"D","25","2021\u002F2020教材P143页 计算工期是根据网络计划时间参数计算出来的工期。本题中，该建设工程施工进度计划的关键路线为：①、②、③、⑦、⑨、⑩。总工期为21天。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]