[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118804":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118804,789,1,"单选题","某工程单代号网络计划如下图所示，节点中下方数字为该工作的持续时间，其关键工作为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工作C和工作E",true,{"key":16,"text":17,"correct":18},"B","工作B和工作E",false,{"key":20,"text":21,"correct":18},"C","工作B和工作D",{"key":23,"text":24,"correct":18},"D","工作A和工作B","2021\u002F2020教材P144页 总时差为0的工作均为关键工作。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]