[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118803":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118803,789,1,"单选题","单代号网络计划时间参数首先应计算( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工作总时差",false,{"key":16,"text":17,"correct":14},"B","工作自由时差",{"key":19,"text":20,"correct":14},"C","相邻两项工作之间的间隔时间",{"key":22,"text":23,"correct":24},"D","最早开始时间和最早完成时间",true,"2021\u002F2020教材P145页 单代号网络计划时间参数的计算步骤如下：1.计算最早开始时间和最早完成时间网络计划中各项工作的最早开始时间和最早完成时间的计算应从网络计划的起点节点开始，顺着箭线的方向依次逐项计算。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]