[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118802":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118802,789,1,"单选题","当工程网络计划的计算工期小于计划工期时，则( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","单代号网络计划中关键线路上相邻工作的时间间隔为O",true,{"key":16,"text":17,"correct":18},"B","双代号网络计划中关键线路上工作的持续时间之和等于计划工期",false,{"key":20,"text":21,"correct":18},"C","双代号网络计划中关键工作的自由时差全部为零",{"key":23,"text":24,"correct":18},"D","单代号搭接网络计划中总时差最小值为O","2021\u002F2020教材P141页 在双代号网络计划中，如果某节点的最早时间与最迟时间相等，说明该节点为关键节点。但以关键节点为开始节点和完成节点的工作不一定是关键工作。即可理解为当工程网络计划的计算工期小于计划工期时，则单代号网络计划中关键路线上相邻工作的时间间隔为0。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]