[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118799":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118799,789,1,"单选题","当计算工期不能满足要求工期时，需要压缩关键工作的持续时间以满足工期要求，则下列选项中不属于选择缩短工作时间应考虑的因素的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","缩短持续时间对质量影响不大的工作",false,{"key":16,"text":17,"correct":14},"B","缩短持续时间所需增加的费用最少的工作",{"key":19,"text":20,"correct":14},"C","有充足备用资源的工作",{"key":22,"text":23,"correct":24},"D","持续时间最长的工作",true,"2021\u002F2020教材P148页 当计算工期不能满足要求工期时，可通过压缩关键工作的持续时间以满足工期要求。在选择缩短持续时间的关键工作时，宜考虑下述因素：(1)缩短持续时间对质量和安全影响不大的工作；(2)有充足备用资源的工作；(3)缩短持续时间所需增加的费用最少的工作等。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]