[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118796":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118796,789,1,"单选题","关于建设工程进度控制，下列说法正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设工程项目中，业主方进度控制的任务是控制整个项目施工阶段进度",false,{"key":16,"text":17,"correct":18},"B","施工方进度控制任务是依据施工合同中施工进度要求控制施工工作进度",true,{"key":20,"text":21,"correct":14},"C","设计方不用考虑设计进度与招标、施工和物资采购等工作进度相协调",{"key":23,"text":24,"correct":14},"D","在国际上设计进度计划主要指确定各设计专业设计图纸的出图计划","2021\u002F2020教材P148页 施工方进度控制的任务是依据施工任务委托合同对施工进度的要求控制施工工作进度",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]