[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118795":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118795,789,1,"单选题","下列选项中，属于施工方进度控制主要工作环节的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","采取纠偏措施",false,{"key":16,"text":17,"correct":14},"B","评审设计方案",{"key":19,"text":20,"correct":14},"C","进度控制工作管理职能分工",{"key":22,"text":23,"correct":24},"D","编制施工进度计划及有关的资源需求计划",true,"2021\u002F2020教材P148页 施工进度控制的任务：施工方进度控制的主要工作环节：①编制施工进度计划及有关的资源需求计划；②组织施工进度计划的实施；③施工进度计划的检查与调查。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]