[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118794":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118794,789,1,"单选题","施工进度计划的内容,不包括()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工作关系",false,{"key":16,"text":17,"correct":14},"B","工作量",{"key":19,"text":20,"correct":14},"C","资源提供条件",{"key":22,"text":23,"correct":24},"D","工程质量",true,"2021\u002F2020教材P149页 进度计划的调整应包括下列内容:工程量的调整;工作起止时间的调整;工作关系的调整;资源提供条件的调整;必要目标的调整。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]