[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118793":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118793,789,1,"单选题","下列各项属于建设工程项目进度控制技术措施的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","编制资源需求计划",false,{"key":16,"text":17,"correct":14},"B","工程进度的风险分析",{"key":19,"text":20,"correct":14},"C","进度控制职能分工",{"key":22,"text":23,"correct":24},"D","选用对实现进度目标有利的施工方案",true,"2021\u002F2020教材P149页 A项属于建设工程项目进度控制的经济措施；B项属于建设工程项目进度控制的管理措施；C项属于建设工程项目进度控制的组织措施。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]