[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118792":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118792,789,1,"单选题","施工进度计划的调整应包括工程量的调整、工作（工序）起止时间的调整、工作关系的调整、必要的目标的调整以及（）的调整。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工预算",false,{"key":16,"text":17,"correct":14},"B","合同约定工期",{"key":19,"text":20,"correct":14},"C","施工管理组织",{"key":22,"text":23,"correct":24},"D","资源提供条件",true,"2021\u002F2020教材P149页 （3）施工进度计划的调整应包括下列内容：1.工程量的调整2.工作起止时间的调整3.工作关系的调整4.资源提供条件的调整5.必要目标的调整。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]