[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118789":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118789,789,1,"单选题","按工作持续时间的特点不同，工程网络计划可划分为( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","肯定型问题网络计划、随机型网络计划和非肯定型问题网络计划",true,{"key":16,"text":17,"correct":18},"B","随机型网络计划、事件型网络计划和分级型网络计划",false,{"key":20,"text":21,"correct":18},"C","双代号网路计划、单代号网络计划和双代号时标网络计划",{"key":23,"text":24,"correct":18},"D","肯定型问题网络计划、非肯定型问题网络计划和分级型网络计划","2021\u002F2020教材P134页 1.工程网络计划按工作持续时间的特点划分为：(1)肯定型问题的网络汁划；(2)非肯定型问题的网络计划；(3)随机网络计划等。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]