[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118787":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":22},1118787,789,1,"单选题","下图双代号网络图中,引入虚工作2-3是为了表示（）。 A.对 A、B两项工作的代号加以区分 B.",[11,15,19],{"key":12,"text":13,"correct":14},"A","B两项工作不能同时结束",true,{"key":16,"text":17,"correct":18},"B","工作A完成后、工作B才能开始",false,{"key":20,"text":21,"correct":18},"C","B两项工作必须同时结束","2021\u002F2020教材P135页 双代号网络图中的虚工作起着工作之间的联系、区分和断路三个作用。本例体现了虚工作的区分作用，即双代号网络图中每一项工作都必须用一条箭线和两个代号表示，若A、B两项工作的代号相同时，应使用虚工作加以区分。 @##",{"id":6,"name":24,"category":25,"favorite":26},"二建建设工程施工管理","建筑工程",0]