[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118786":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118786,789,1,"单选题","双代号网络图的组成要素是指（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","时差、最早时间、最迟时间",false,{"key":16,"text":17,"correct":14},"B","总时差、局部时差、计算工期",{"key":19,"text":20,"correct":21},"C","工作、节点、线路",true,{"key":23,"text":24,"correct":14},"D","工作、节点、关键线路","2021\u002F2020教材P135页 箭线（工作），节点（又称结点，事件）和线路，逻辑关系",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]