[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118780":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118780,789,1,"单选题","（ ）是进度控制的依据。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工进度目标",false,{"key":16,"text":17,"correct":14},"B","施工进度计划",{"key":19,"text":20,"correct":14},"C","旋工的总体部署",{"key":22,"text":23,"correct":24},"D","实现进度目标的里程碑事件的进度目标",true,"2021\u002F2020教材P133页 控制性施工进度计划编制的主要目的是通过计划的编制，以对施工承包合同所规定的施工进度目标进行再论证，并对进度目标进行分解，确定施工的总体部署，并确定为实现进度目标的里程碑事件的进度目标(或称其为控制节点的进度目标)，作为进度控制的依据。故选D。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]