[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118777":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118777,789,1,"单选题","下列单代号网络计划中，关健工作是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","A—B—C—E—G",true,{"key":16,"text":17,"correct":18},"B","A—B—D—F—G",false,{"key":20,"text":21,"correct":18},"C","A—B—D—E—G",{"key":23,"text":24,"correct":18},"D","A—B—E—G","2021\u002F2020教材P137页 在各条线路中，有一条或几条线路的总时间最长，称为关键路线，一般用双线或粗线标注。其他线路长度均小于关键线路，称为非关键线路。关键线路上的工作为关键工作。关键工作：A-B-C-E-G。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]