[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118776":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118776,789,1,"单选题","某双代号网络计划如图所示（时间单位：d），则该计划的关键线路是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①-②-④-⑤-⑥-⑦",true,{"key":16,"text":17,"correct":18},"B","①-②-④-⑤-⑦",false,{"key":20,"text":21,"correct":18},"C","①-③-④-⑤-⑥-⑦",{"key":23,"text":24,"correct":18},"D","①-③-④-⑤-⑦","2021\u002F2020教材P137页 在各条线路中，有一条或几条线路的总时间最长，称为关键路线，一般用双线或粗线标注。其他线路长度均小于关键线路，称为非关键线路。关键线路：1-2-4-5-6-7，工期14天。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]