[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118774":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118774,789,1,"单选题","已知某建设工程网络计划中A工作的自由时差为3天，总时差为5天。监理工程师在检查施工进度时发现只有该工作实际进度拖延，且影响总工期3天，则该工作实际进度比计划进度拖延()天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":14},"B","5",{"key":19,"text":20,"correct":21},"C","8",true,{"key":23,"text":24,"correct":14},"D","10","2021\u002F2020教材P139页 总时差是指在不影响总工期的前提下，工作可以利用的机动时间。影响工期3天，所以总时差5天+影响的3天=8天",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]