[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118773":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118773,789,1,"单选题","某工程单代号网络计划如下图所示，其关键线路为()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1—2—4—6",false,{"key":16,"text":17,"correct":14},"B","1—3—4—6",{"key":19,"text":20,"correct":21},"C","1—3—5—6",true,{"key":23,"text":24,"correct":14},"D","1—2—5—6","2021\u002F2020教材P139页 自始至终全部由关键工作组成的线路为关键线路，或线路上总的工作持续时间最长的线路为关键线路。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]