[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118771":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118771,789,1,"单选题","某网络计划中，工作A的紧后工作是B和 C，工作B的最迟开始时间为15，最早开始时间为9；工作C的最迟完成时间为16，最早完成时间为13；工作A与工作 B、C的时间间隔均为4d，则工作A的总时差为().",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":18},"B","7",true,{"key":20,"text":21,"correct":14},"C","8",{"key":23,"text":24,"correct":14},"D","10","2021\u002F2020教材P139页 总时差指不影响总工期的前提下，工作可以利用的机动时间。A工作的总时差=A工作的自由时差+min{其紧后工作总时差}=4+min{15-9，16-13）=7",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]