[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118770":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118770,789,1,"单选题","某建设工程网络计划中某工作的自由时差为4d，总时差为5d。施工进度检查时发现该工作实际进度拖延导致总工期拖延2d，其他工作未拖延。则该工作实际进度比计划进度拖延()d。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","2",false,{"key":16,"text":17,"correct":14},"B","6",{"key":19,"text":20,"correct":21},"C","7",true,{"key":23,"text":24,"correct":14},"D","11","2021\u002F2020教材P139页 总时差是指在不影响总工期的前提下，工作可以利用的机动时间；自由时差是指在不影响其紧后工作最早开始的前提下，工作可以利用的机动时间。故本题中，实际进度比计划进度拖延的时间为2d+5d=7d。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]