[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118769":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118769,789,1,"单选题","已知在双代号网络计划中，某工作有2项紧前工作，它们的最早完成时间分别为18天和23天。如果该工作的持续时间为6天，则该工作最早完成时间为()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","18天",false,{"key":16,"text":17,"correct":14},"B","23天",{"key":19,"text":20,"correct":14},"C","24天",{"key":22,"text":23,"correct":24},"D","29天",true,"2021\u002F2020教材P139页 最早完成时间等于最早开始时间加上其持续时间，23+6=29天。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]