[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118768":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118768,789,1,"单选题","当某工程网络计划的计算工期等于计划工期时，该网络计划中的关键工作是指( )的工作。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","时标网络计划中没有波形线",false,{"key":16,"text":17,"correct":14},"B","与紧后工作之间时间间隔为零",{"key":19,"text":20,"correct":14},"C","开始节点与完成节点均为关键节点",{"key":22,"text":23,"correct":24},"D","最早完成时间等于最迟完成时间",true,"2021\u002F2020教材P140页 总时差等于其最迟开始时间减去最早开始时间，或等于最迟完成时间减去最早完成时间。网络计划中总时差最小的工作是关键工作。D选项为总时差为0。题意给的计算工期等于计划工期，最小为就是等于0。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]