[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118767":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118767,789,1,"单选题","在工程网络计划中，工作M的最迟完成时间为25天，其持续时间为7天。如果工作M最早开始时间为13天，则工作M的总时差为()天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5",true,{"key":16,"text":17,"correct":18},"B","6",false,{"key":20,"text":21,"correct":18},"C","7",{"key":23,"text":24,"correct":18},"D","12","2021\u002F2020教材P140页 最迟开始时间为最迟完成时间减去其持续时间，（25-7=18天）； 总时差等于最迟开始时间减去最早开始时间，（18-13=5天）。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]