[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118766":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118766,789,1,"单选题","已知下列双代号网络图，其中工作J的最早完成时间为（）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","4",false,{"key":16,"text":17,"correct":14},"B","6",{"key":19,"text":20,"correct":21},"C","9",true,{"key":23,"text":24,"correct":14},"D","11","2021\u002F2020教材P140页 工作最早开始时间等于各紧前工作的最早完成时间的最大值，题目中J工作有2项紧前工作E和F，它们最早完成时间的分别为4天和5天，则J工作最早开始时间等于5天。J工作最早完成时间等于最早开始时间加上其持续时间5+4=9天。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]