[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118763":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118763,789,1,"单选题","业主方进度控制的任务是控制整个项目实施阶段的进度，不包括控制()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","设计准备阶段的工作进度",false,{"key":16,"text":17,"correct":14},"B","物资采购工作进度",{"key":19,"text":20,"correct":21},"C","征地拆迁工作进度",true,{"key":23,"text":24,"correct":14},"D","项目动用前准备阶段工作进度","2021\u002F2020教材P131页 业主方进度控制的任务是控制整个项目实施阶段的进度，包括控制设计准备阶段的工作进度、设计工作进度、施工进度、物资采购工作进度以及项目动用前准备阶段的工作进度。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]