[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118762":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118762,789,1,"单选题","建设工程项目进度控制的任务中，业主方进度控制的任务是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","依据设计任务委托合同对设计工作进度的要求控制设计工作进度",false,{"key":16,"text":17,"correct":18},"B","控制整个项目实施阶段的进度",true,{"key":20,"text":21,"correct":14},"C","依据施工任务委托合同对施工进度的要求控制施工工作进度",{"key":23,"text":24,"correct":14},"D","编制深度不同的控制性和直接指导项目施工的进度计划","2021\u002F2020教材P131页 业主方进度控制的任务是控制整个项目实施阶段的进度。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]