[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118761":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118761,789,1,"单选题","在理论上和工程实践中，一般而言，工程项目的控制性施工进度计划是指( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","单位工程施工进度计划",false,{"key":16,"text":17,"correct":14},"B","施工企业年度生产计划",{"key":19,"text":20,"correct":21},"C","工程项目施工总进度规划",true,{"key":23,"text":24,"correct":14},"D","工程项目月度施工计划","2021\u002F2020教材P132页 以上列举了许多进度计划的名称，在理论上和工程实践中并没有非常明确的界定。何为控制性进度计划。一般而言，一个工程项目的施工总进度规划或施工总进度计划是工程项目的控制性施工进度计划。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]