[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118759":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118759,789,1,"单选题","下列建设工程项目进度控制工作中，属于施工方进度控制任务的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","部署项目动用准备工作进度",false,{"key":16,"text":17,"correct":14},"B","协商设计、招标的工作进度",{"key":19,"text":20,"correct":21},"C","编制项目施工的工作计划",true,{"key":23,"text":24,"correct":14},"D","编制供货进度计划","2021\u002F2020教材P131页 施工进度控制的任务是依据施工任务委托合同对施工进度的要求控制施工工作进度，这是施工方履行合同的义务，在进度计划编制方面，施工方应视项目的特点和施工进度控制的需要，编制深度不同的控制性和直接指导项目施工的进度计划，以及按不同计划周期编制的计划，如年度、季度、月度和旬计划等。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]