[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118755":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118755,789,1,"单选题","设计单位进度控制的任务是依据（）对设计工作进度的要求控制设计工作进度。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建设项目总进度目标",false,{"key":16,"text":17,"correct":14},"B","设计总进度计划",{"key":19,"text":20,"correct":14},"C","工程工期",{"key":22,"text":23,"correct":24},"D","设计委托合同",true,"2021\u002F2020教材P131页 设计方进度控制的任务是依据设计任务委托合同对设计工作进度的要求控制设计工作进度，这是设计方履行合同的义务。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]