[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118754":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118754,789,1,"单选题","如果一个进度计划系统由总进度计划,项目子系统进度计划,项目子系统的单项工程进度计划组成。该进度计划系统是由()的计划组成的计划系统。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","不同功能",false,{"key":16,"text":17,"correct":14},"B","不同项目参与方",{"key":19,"text":20,"correct":21},"C","不同深度",true,{"key":23,"text":24,"correct":14},"D","不同周期","2021\u002F2020教材P129页 由不同深度的计划构成的进度计划系统包括:总进度计划、项目子系统进度计划、项目子系统的单项工程进度计划。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]