[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118753":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118753,789,1,"单选题","在建设工程项目进度计划系统中，由业主方、设计方、施工和设备安装方编制的进度计划应与（）编制的进度计划相互协调。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","监理方",false,{"key":16,"text":17,"correct":18},"B","采购和供货方",true,{"key":20,"text":21,"correct":14},"C","投资方",{"key":23,"text":24,"correct":14},"D","政府行政主管部门","2021\u002F2020教材P130页 (3)业主方编制的整个项目实施的进度计划、设计方编制的进度计划、施工和 设备安装方编制的进度计划与采购和供货方编制的进度计划之间的联系和协调等。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]