[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118752":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118752,789,1,"单选题","下列建设工程项目进度计划中，不属于由不同项目参与方的计划构成的进度计划系统的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","业主方编制的整个项目实施的进度计划",false,{"key":16,"text":17,"correct":14},"B","设计进度计划",{"key":19,"text":20,"correct":21},"C","实施性进度计划",true,{"key":23,"text":24,"correct":14},"D","施工和设备安装进度计划","2021\u002F2020教材P130页 由不同项目参与方的计划构成的进度计划系统包括：(1)业主方编制的整个项目实施的进度计划；(2)设计进度计划；(3)施工和设备安装进度计划；(4)采购和供货进度计划等。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]